Force All Equipment Actions

Note: You must have the “Enable Client Re-Sync Operations” checkbox checked for this to be enabled.

This command is like the re-sync command except that it will force ALL equipment items into their correct states instead of just the ones that are out-of-sync.  You will get the same manual re-sync dialog with the “Forced Re-Sync” option checked.  You can also individually select equipment items as the example shows below.

Graphical user interface, text, application, email

Description automatically generated

This is useful for example if you have a power outage and the default state for all your HVAC zones is OFF.  This will resend the commands for each zone to the current state of the calendar and get the occupied zones going again.

If you want to perform the “Forced Re-Sync” operation automatically, there is an option to enable a forced re-sync task that will automatically run the operation daily at a certain time.

See:  Schedule Processing Tab